FEWA has initiated the Water Supply Works as earlier stated.
The Pipeline installation has started from Fortune Residency (Plot C-01) and progressing towards Goldcrest Dreams (Plot C-09).
It is appreciated that they are sticked to the timeline and progressing well.
However, it is also noted that the pipeline installation heavily depends upon the clearance of the land area in front of towers, that are under construction. Huge machinery and construction material is stored above the land from which underneath the lines are needed to go.
Hopefully ‘The Developers’ might be notified and should be cooperative as the community has already suffered alot.